The City of Cape Town thanks customers for their patience as we do necessary routine maintenance on our electrical infrastructure next week in various areas of the metro. This is how we ensure reliable electricity supply and good management of our public infrastructure. We encourage residents to always double check on the City’s social media channels to see if their area will be affected by the regular electricity maintenance during the week. Where customers are affected by supply interruptions due to normal maintenance, they should receive a door-to-door notice ahead of the planned work.

 

PLANNED ROUTINE ELECTRICITY MAINTENANCE 28 March – 3 April 2022

 

DATE     AREA     LOCATION/STREET          START   COMPLETION FORECAST

29 March             Somerset West Beaulie and Bakkerskloof Rd      08:00     18:00

29 March             Kuils River – Amandelrug             Manatoka, Kerk, Olienhout, Piet Fransman, Keurboom, Walnut, Pruim, Goudwilger, Hardekool, Fisant, Du cup, Kiepersol, Pendoring, Kameeldoring, Kanabos and Geelhout    08:30                16:00

29 March             Somerset West Elsenham, Pierneef, Heide,  Montrose, Harrison and Durban    08:00     18:00

29 March             Somerset West Elsenham, Acton, Heide and De Bloem 08:30     18:00

29 March             Bonteheuwel    Apricot and Boekenhout substations     08:30     16:00

29 March             Hout Bay             Main, Brink, Hout Bay and the International School        09:00     16:00

29 March             Newlands          

Main and Kildae

 

09:00     16:00

29 March             Newlands           SACS school, Irene, Dean, Newlands      09:00     16:00

29 March             Newlands           Sharock, Thorn and vicinity         09:00     16:00

30 March             Maitland            

Green and Loco

 

08:00     16:00

30 March             Kuils River – Amandelsig              Hoop, Namakwa, Verreweide, Populier, Plantanus, Middel, Spruit, Jacobs, Kwartel, Nagtegaal, Diedrikkie, Piet my vrou, Tarentaal, Tinktinkie, Bokmakierie, Bosonia, Mossie, Syringa, Eerste, Tweede, Derde, Vierde, Komos, Seemeeu, Kiewiet and Sonnemeisie   09:00     14:00

30 March             Strand   George and vicinity        08:30     18:00

30 March             Langa    Jungle walk substation 08:30     17:00

30 March             Epping  Spring Gardens, Lonsdale Way, Pinelands Place and Pinewood Park      08:30     16:00

31 March             Goodwood         Beaufort and Voortrekker           07:30     14:30

31 March             Somerset West West Riding       08:00     18:00

31 March             Maitland             Loco and Spoorbaan       08:00     16:00

31 March             Mowbray            Broad, Alma, Montreal and Kotzee         08:00     16:00

31 March             Goodwood         Beaufort and vicinity     08:00     13:00

31 March             Strand   Wesley, Tulbagh and vicinity     08:30     18:00

31 March             Bellville               Labiance and Sirrocco villiage    09:00     16:00

31 March             Claremont          Lincoln and vicinity         09:00     16:00

1 April   Athlone               Garlandale, Lascalles, Conningsby and Woodside Estate              08:30     16:30

2 April   Lentegeur           Sesame, Candytuft and Plumbago           08:00     20:00

2 April   Mowbray            Surrey and Montreal      08:00     16:00

2 April   Pinelands            Park       08:00     16:00

3 April   Westridge          Avocado, Avocado close, Dagbreek, Amandel, Amandel Close, La Provence, La Provence Close, Kronedal                08:00     20:00

3 April   Epping  Bofors circle       08:00     16:00

3 April   Maitland and Forshore Port industries and Milnerton Estate     08:00     16:00

 

*Information is complete and correct at time of publication, but subject to change due to weather and other unforeseen conditions.

*It is standard practice to notify customers of planned maintenance via a pamphlet delivered door-to-door ahead of work.

 

Tips:

 

  • Where possible, please switch off appliances at the wall socket ahead of maintenance to reduce the risk of damage caused by power surges.
  • The supply could be restored at any time, therefore residents should remember to treat all electrical installations as live for the full duration of the interruption.

 