Eskom’s Kusile Unit 4 added to power grid

Eskom has connected Unit 4 of Kusile Power Station project to the national grid.

The unit was connected to the grid for the first time on 23 December.

“This synchronisation milestone means four generating units of the power station are now connected to the grid, and will contribute an additional 800MW to the country’s power system once the unit is fully optimised, following a series of tests and other commissioning activities,” said the power utility on Thursday.

Situated near eMalahleni in Mpumalanga, Kusile is South Africa’s largest construction project and will be the world’s fourth largest coal plant.

The unit will supply electricity intermittently during the testing and optimisation phase over the next six months, before being handed over to the Generation division to officially be part of the commercial fleet.

This will further assist Eskom to address supply capacity challenges.

Group Executive for Group Capital, Bheki Nxumalo, said the milestone is just what the country needs to power the economy.

“This achievement signifies the relentless efforts from the team in ensuring that the power station project is completed without any further delays, which would help strengthen South Africa’s electricity capacity. I am grateful for the commitment displayed by the Kusile Execution Team and its contractors.”

Since synchronization last week, the unit has performed to expectation, intermittently generating up to 330MW. Eskom said the unit post synchronization commissioning activities are well in progress, and experiencing the normal challenges, as expected, during this phase.

Construction and commissioning activities on the remaining Kusile Units 5 and 6 continue to progress according to plan.

At completion, the station will consist of six units, and will produce a maximum 4 800MW.

Eskom is fitting wet flue gas desulphurisation (WFGD) to the Kusile plant as an atmospheric emission abatement technology, in line with current international practice, to ensure compliance with air quality standards, making it more environmentally friendly.

Kusile is the first power station in South Africa and Africa to use WFGD technology. WFGD is state-of-the-art technology used to remove oxides of sulphur (SOx), for example, sulphur dioxide (SO2), in the emmissions of power plants that burn coal or oil.

 

Source: South African Government News Agency